  • New residential development on five individual adjacent sites and construction of seven new adopted highways across the development site.
  • 192 houses and flats across the development as a whole.
  • Site originally occupied by housing and access roads to different layout.
  • Temporary works and demolition sequencing for demolition of high rise block of flats.
  • Liaison with Statutory Service undertakers to identify and cost diversions and agree programming of diversions.
  • Serving of stopping up orders to remove existing public highway areas.
  • All negotiation and detailing of Section 38 and section 278 highway matters relating to creation of new roads.
  • All negotiation and detailing of Section 104 and Building Over matters relating to Public Sewers serving the site.
  • Detailed structural design of all new dwellings.